Gaglardi Way Bridge
Client: City of Burnaby
Location: Burnaby, BC
Value: $1,271,388,63
Completion date: February, 2014
Project Synopsis:
- Remove and replace unsuitable backfill
- Culvert removal and bio swale
- Ship out, form, and pour deck drains
- Railing modifications
- Additional east parapet reinforcing
- Deck concrete scarification, local deck sub-excavating, concrete demolition, push through abutment works, bicycle railing, abutment deck drain plugs